Project Details
Contractor |
Balfour Beatty |
Description |
The dry changing areas and poolside wet changing areas are being extended and refurbished and to be tiled throughout. The foyer, circulation areas, fitness suite and creche facilities are to be refurbished and finished in various carpets, high impact rubber matting and slip resistant vinyls. |
Time on Site |
5 phases over 6 months |
Value of Project |
Soft flooring £41,482 and tiling £57,000 |
Category / Work |
Soft Flooring and Tiling |
Sq m of tiles |
Tiling circa 850sq m and Soft Flooring circa 800sq m |